Construction Update

Amara City Gardens is in its final stages and close to completion!

July 2022

Works completed over the previous month:

  • Kitchen cabinets complete to all apartments and advanced to level 3 dining & wine cellar.
  • Finishing trades to common areas (ground, level 3 & level 4) progressing well.
  • Artist Anne Neil designed perforated screens to carpark & ground level awning almost complete.
  • Landscaping works have commenced to all common areas.
  • Sandstone cladding to ground floor commercial tenancies nearing completion.

June 2022

Works that have occurred over the month of June:

  • Lift installation complete
  • External windows remaining to ground floor
  • Wall & sheeting to Level 3 Dining Pavilion
  • Cabinetry installation to Level 3 Dining Pavilion
  • Wine Cellar progressing
  • Awning and Frames for perforated aluminum screens
  • Common areas progressing, screeding to Level 4 arbour area
  • Defecting / snagging ongoing on upper levels and process working well with the architect team

May 2022

The construction at Amara has continued to progress at a consistent rate thanks to BCG. The internal lifts are now fully operational, and the external builders lift is to be dismantled this week. Scaffolding has been removed and the site crane demobilised. Internal tiling, cabinetry and finishes are continuing to advance throughout the building. A display apartment on level 8 has been fully completed and beautifully furnished for new buyers to inspect, you can view the virtual reality video here https://my.matterport.com/show/?m=cLFmFQjRsnX. We are currently limiting viewing to new buyer appointments only as it is still an active construction site and bookings are very restricted for safety reasons.

March 2022

  • Structure now complete
  • Scaffold removed to tower.
  • Services fit off moving through all levels.
  • Kitchen cabinets installed through Level 14.
  • Defecting occurring through lower levels.
  • Lift installation well advanced and builders lift due 14 April
  • Tower crane removed

February 2022

Amara site crane has been demobilised and scaffolding is continuing to come down.

January 2022

Scaffolding is coming down!

December 2021

Views from the top! Amara has topped out and scaffolding is starting to come down.

October 2021

Upcoming works for the next month include:

  • Level 13 slab complete;
  • Level 14 slab formed and well advanced;
  • Concrete lift pit, the last of concrete structure, estimated to be complete early November
  • Vertical structural elements progressing with slabs;
  • Stud framing and sheeting up to level 9;
  • Service reticulation moving with stud framing ad sheeting;
  • Kitchen cabinets complete to level 4 and commenced level 5;
  • Screed and tiling to wet areas and balconies levels 1, 2 & 4 and
  • Window frame and glass installation moving through level 9.

August 2021 Level 9 slab going down!

North West view out to the Swan River

July 2021

  • Level 6 slab well advanced
  • Slabs to be completed every fortnight moving forward (dependent on favourable weather)
  • Lift core advancing ahead of slabs
  • Vertical structural elements progressing with slabs
  • Podium level internal walls and linings advanced, commenced to tower level.
  • Kitchen cabinets commenced to podium level apartments
  • Services being reticulated through carpark and podium level apartments
  • Paint to lower level precast panels advanced.
  • Window frame and glass commenced to podium level apartments

July 2021

On the ground level you’ll find the residents gym and commercial tenancies, levels 1 & 2 are one bedroom apartments- all have sold out! On level 3 the private dining room and wine cellar, yoga deck, barbeque pavilion and sun deck is being built.

June 2021

May 2021

Upcoming works for the next month include:

  • Level 2 suspended slab complete;
  • Level 3 suspended slab well advanced;
  • Level 4 slab reasonably commenced;
  • Precast panels to perimeter and column structure advancing with slabs;
  • Lift and stair core jump-form system progressing ahead of slabs;
  • Service reticulation through carpark areas commenced;
  • Infill walls will progress as back propping is removed

April 2021 Jumpforms are in and levels are going up!

March 2021 Level 1 concrete is being poured!

March 2021 The crane is up!

February 2021 - Bulk earthworks advanced

January 2021 More progress on excavation

January 2021 Ground establishing works now well advanced to allow major works to commence.